Primary School Renovations

  • restrooms


  • We are proud to be working with Infinity Construction on the Copley High School, Copley-Fairlawn Middle School, Arrowhead Primary, Fort Island Primary, and Herberich Primary School renovation!

    November 2024

    After working throughout the summer and the early part of the school year, we are excited to report the final walk-through of all the primary school restrooms is scheduled for December 2, 2024. The blue and gold tile looks great in both the boys/girls group restrooms, classroom restrooms, and single use restrooms.  If you are at one of the primary schools be sure to check out how nice these restrooms turned out!

    June 2024

    APS restrooms have gone through the demo phase. Plumbers and electricians are working hard in these areas to change our plumbing and electrical systems.  Demo at FIPS has begun and should be completed by the end of the week.  At HPS the crews have relocated the backflow system.  Demolition will be started at HPS by the end of June.

    May 2024

    Permits have been received for APS, HPS, and FIPS!   Demolition is scheduled at all 3 primary buildings on May 31.  We are excited to get these interior projects started!

    April 2024

    Infinity Construction has been busy planning, ordering, and prepping for construction to start at  APS, FIPS, and HPS.  This month a construction trailer was set in place at CHS to house the primary school construction team.

    March 2024

    Infinity Construction has been meeting with the district team to review plans and secure materials for this project.  The demolition and renovation of all primary school restrooms is expected to begin as soon as school concludes for the 23-24 school year.

    February 2024

    The design and construction document phase for the Arrowhead, Herberich, and Fort Island Primary Schools restroom renovations has been completed.  Bid openings for this project (as well as the Copley High School and Copley-Fairlawn Middle School interior projects) was held on February 7, 2024, at 12:00 p.m. at Copley-Fairlawn City Schools Board of Education Office.  Subsequently, a special board meeting was held on Tuesday, February 13, 2024, to award the bid to Infinity Construction.  We are very excited to begin working with Infinity Construction on our interior projects at all five school buildings.