CHS & CFMS Renovations


  • We took one of our staff members on a behind-the-scenes tour of the construction at CHS and CFMS.  Check out the video to see what he discovered and the progress at CHS and CFMS!

    July Inside Peek

    July 2024 Inside Peek

     


  • We are proud to be working with Infinity Construction on the Copley High School, Copley-Fairlawn Middle School, Arrowhead Primary, Fort Island Primary, and Herberich Primary School renovation!

     

    June 2024

    We received the permit from Summit County on June 6th for CHS.  Since that time, the demolition crews have been hard at work.  Demolition on the kitchen, commons, Bistro kitchen, and lobby have been completed.  Bathroom demolition has started and lockerroom demo will begin in the next couple of weeks.  At CFMS demolition has been completed on the cafeteria, kitchen, locker rooms, and most restrooms.  The focus in these areas is now on plumbing, electrical work, and flooring.

    May 2024

    Permits have been received for APS, HPS, and FIPS.  We are still waiting on permits for Copley High School.  Work has started at CFMS in the locker room and restrooms on the basement level.  Work in the cafeteria and kitchen is scheduled to begin on 5/23.  Demolition is scheduled at all 3 primary buildings on May 31.  We are excited to get these interior projects started!

    April 2024

    Infinity Construction has been busy planning, ordering, and prepping for construction to start at CFMS, APS, FIPS, and HPS.  We are still waiting on final permits for Copley High School and the 3 primary buildings. 

    March 2024

    The Infinity Construction trailer (office) has been put in place and traffic is being rerouted in anticipation for the front circle drive of the high school to be closed.  We are currently waiting for the demolition permits for the projects.  As soon as those are issued you will start to see activity on the front entrance of the high school building.

    February 2024

    Bid openings for this project (as well as the three primary school building interior projects) was held on February 7, 2024, at 12:00 p.m. at Copley-Fairlawn City Schools Board of Education Office.  Subsequently, a special board meeting was held on Tuesday, February 13, 2024, to award the bid to Infinity Construction.  We are very excited to begin working with Infinity Construction on our interior projects at all five school buildings.

    January 2024

    The design and construction document phase for projects at both Copley High School and Copley-Fairlawn Middle School has been completed.  Bid openings are scheduled to be held on February 7, 2024 at 12:00 p.m. at Copley High School in the auditorium.  Projects included are:

    • Restrooms & Locker Rooms
    • Kitchens & Cafeterias
    • CHS Auditorium 
    • CHS Main Entrance